A new storm cycle is passing through the valley this week and while it is mostly blustery, we are grateful to see some accumulation. (Here's hoping for more snow to wrap up the ski season and to setup a great summer!) It has been a busy month at Brush Creek Village with the last four-bedroom unit in Phase 1 closing and the remaining three-bedroom units going under contract in the last week. With sales in Phase 1 concluding, we can shift our full focus to Phase 2. Progress continues in the first two buildings, Buildings D and F. Flooring is being installed in Building D and the interior railings are being fabricated and installed. Interior doors are on site and being prepped for installation. Cabinets are scheduled to be delivered later this month. Insulation is being installed throughout Building F with drywallers scheduled to start next week. Framing for the last two buildings, Buildings B and H, will commence in April (weather dependent).